GANGTOK: Men
and machines are racing against time to complete the work on the Teesta – Stage
III Hydro Electric Project which is expected to mitigate the ongoing power
crisis in the tiny Himalayan State.
Sikkim which is endowed with vast hydro power potential
and Teesta is the main river stream in Sikkim. The potential of Teesta River is
being harnessed through a cascade of six Hydro projects.
The 1200 MW Teesta-III is part of this cascade development
– the highest capacity power project in Sikkim.
The Teesta Project was conceived as part of cascade
development of river Teesta by CWC in the year 1974. An SPV called “Teesta Urja
Limited” was formed in April 2005 and Implementation agreement signed with the
Sikkim Government in July 2005.
The project received all statuary clearances in Record
time. The construction is being executed
under EPC by a consortium led by M/s Navayuga Engineering Company Ltd.
As much as 99.2% of Tunneling Works completed (around
34.4 Km out of total 34.6 Km). The Excavation of 13.824 Km of Head Race Tunnel was
also completed.
Power produced to be transmitted till Kishenganj through
400 KV DC line to be constructed by Teesta valley Power Transmission , a JV
between Teesta Urja Ltd
and Power grid Corporation of India Limited (PGCIL).
PGCIL is to wheel the power to the beneficiary states in the northern region
beyond Kishenganj.
The positive news about the progress of Teesta-III comes
as a big relief to the people of Sikkim who are bracing themselves to pay
higher tariff.
Power Secretary AK Giri had said that the state currently
is procuring electricity from NTPC and thermal power is subject to vagaries of
coal supply and prices. As such the price per unit Rs 3 will be applicable from
this month itself, Mr Giri said.
Latest
updates of Teesta-III
- The
Project is conferred with Mega Project Status by the Ministry of Power,
Government of India on 2nd June 2010.
- River
Diversion achieved on 15th January 2010.
- Around
99.4% of cumulative tunneling completed in the project.
- 71%
of the Rock filling completed in Concrete Face Fill Dam (CFRD).
- Cut
off Wall Excavation works commenced in Dam Site.
- HRT
Excavation achieved on June 4, 2011. Till date 5856 m of overt lining
completed.
- Surge
Shaft - Break Through achieved between the pilot hole and sinking face on
July 8, 2011.
- Vertical
Pressure Shaft 1 (645 m): Excavation completed.
- Vertical
Pressure Shaft 2 (645 m): Break Through achieved between the pilot hole
and sinking face on July 30, 2011.
- Electro-Mechanical
works commenced in all six units.
- Steel
liners erection commenced in Pressure Shaft.
No comments:
Post a Comment